Transportation70+AK/AL/AR +moreConstruction & Safety39+CAEnvironmental99+AL/AR/AZ +moreHealthcare & Clinical196+AL/AR/AZ +moreProfessional Licensing307+AL/AR/AZ +moreEducation & Teacher Certification24+CAAviation & FAA Certification9Finance & Securities Licensing23IT & Cloud Certification6Project Management1Military Entrance Testing1View all sectors โ€บ

Free PMP Practice Exam Online

Official exam: PMP Practice Exam (2026 Exam Content Outline)

Take a free PMP practice exam online: a full 180-question paper with every answer explained, no sign-up, scored by topic. The full 360-question bank and the timed simulator are $14.99 for 30 days.

First published: September 13, 2026Bank updated: September 13, 2026Published by CertQuestUSA ยท review process
TL;DR

PMP Practice Exam (2026 Exam Content Outline): a 360-question practice bank for the real Project Management standard, 2 full papers of 180 questions each with no repeats, every question written to the exam sponsor's published content outline.

Where these questions come from

Every question in this bank cites a source -- primarily PMP ECO 2026 Process Task (41%) and PMP ECO 2026 People Task (33%) of this exam's citations.

Take a full practice test free. 180 real questions built to the exam's domain weights, every answer explained, no sign-up required, with a domain-by-domain score at the end.
Start diagnostic
Want the whole bank for PMP Practice Exam (2026 Exam Content Outline)? One payment of $14.99 gives you 30 days of full access to this exam. It does not renew. No account needed to buy, and there is a 7-day money-back guarantee.
Not ready yet? Take the free practice test first.
Ways to pay for the full bank
30-day pass
$14.99
about $15 a month
This exam only. Pays once, does not renew.
Monthly
$19.99
$19.99 a month
Every exam. Cancel any time.
Yearly
$143.93
about $11.99 a month
Every exam. Billed once a year.
Lifetime
$39.99
pay once
This exam only, no time limit.

See all plans and bundles

2
full papers, no repeats
180
questions per paper
360
questions in the bank
What this exam covers
5 real sample questions
A project manager on a two-year project learns that the organisation's borrowing costs are expected to rise sharply next year, and that the project's second-year spend is funded by borrowing. What should the project manager do?
A. Reduce scope to eliminate year-two spend
B. Accelerate all spend into year one
C. Ignore it since interest rates are outside the project's control
D. Anticipate the finance challenge by assessing the impact on project cost and raising it with the sponsor and finance for a decision on options
Show answer and reasoning

Correct answer: D. Anticipate the finance challenge by assessing the impact on project cost and raising it with the sponsor and finance for a decision on options

Correct: anticipating future finance challenges is a Process Task 6 enabler.

  • A: Scope cuts are a decision for the sponsor after assessment.
  • B: Acceleration may not be feasible or wise without analysis.
  • C: External factors can affect project finances and should be assessed.
Source: PMP ECO 2026 Process Task 6
A sponsor asks an agile project manager for a financial report showing the value delivered per unit of spend so far, not just the amount spent. What should the report include?
A. The number of sprints completed
B. A list of team members and their rates
C. Story points delivered per sprint
D. Cumulative spend alongside delivered outcomes or benefit measures per increment, so the sponsor can see value against cost
Show answer and reasoning

Correct answer: D. Cumulative spend alongside delivered outcomes or benefit measures per increment, so the sponsor can see value against cost

Correct: planning financial reporting under Process Task 6 should meet the sponsor's need, which here is value against cost.

  • A: Sprint count says nothing about value or spend.
  • B: Rates describe cost inputs, not value.
  • C: Story points are effort, not value.
Source: PMP ECO 2026 Process Task 6
A hybrid project manager notices that the team's quality checks are done only at major milestones every three months. Problems found at milestones require extensive rework. What should the project manager do?
A. Keep milestone reviews since they are in the plan
B. Remove the milestone reviews to save time
C. Add more people to the milestone reviews
D. Introduce ongoing quality reviews at shorter intervals so problems are found and corrected early
Show answer and reasoning

Correct answer: D. Introduce ongoing quality reviews at shorter intervals so problems are found and corrected early

Correct: conducting ongoing quality reviews is a Process Task 7 enabler. Frequent checks reduce rework.

  • A: The plan can be improved when it is producing costly rework.
  • B: Removing reviews removes the only quality control.
  • C: More reviewers at a late review still finds problems late.
Source: PMP ECO 2026 Process Task 7
A hybrid project manager notices that the contingency reserve is being used to fund small scope additions requested by stakeholders rather than identified risks. Half the reserve is gone with most risks still open. What should the project manager do?
A. Ask for a larger reserve
B. Stop using contingency for scope changes, route those requests through change control with their own funding decision, and report the reserve position to governance
C. Refuse all stakeholder requests
D. Continue since the reserve is there to be spent
Show answer and reasoning

Correct answer: B. Stop using contingency for scope changes, route those requests through change control with their own funding decision, and report the reserve position to governance

Correct: managing financial reserves is a Process Task 6 enabler. Contingency is for risks, and misuse must be corrected and reported.

  • A: Enlarging a misused reserve does not fix the misuse.
  • C: Requests may be valid; they need proper handling, not refusal.
  • D: The reserve's purpose is risk response, not discretionary scope.
Source: PMP ECO 2026 Process Task 6
An agile project is being planned. The sponsor asks the project manager for the total effort estimate and the resource plan before the first sprint. The team has only a high-level backlog. What should the project manager do?
A. Give a single precise figure to satisfy the sponsor
B. Ask the sponsor to fund the project without an estimate
C. Provide a range estimate based on the high-level backlog and team capacity, explain the uncertainty, and commit to refining it as the backlog is elaborated
D. Refuse to estimate until the backlog is fully detailed
Show answer and reasoning

Correct answer: C. Provide a range estimate based on the high-level backlog and team capacity, explain the uncertainty, and commit to refining it as the backlog is elaborated

Correct: estimating work effort and resource requirements is a Process Task 1 enabler. In adaptive projects, early estimates are ranges refined over time, and that should be explained.

  • A: False precision misleads the sponsor and sets up a broken expectation.
  • B: Funding decisions require some basis; asking for a blank cheque is unrealistic.
  • D: Sponsors need an estimate to decide; refusing is unhelpful.
Source: PMP ECO 2026 Process Task 1

Frequently asked questions

Where can I take a free PMP practice exam online?
Right here. CertQuestUSA's free PMP practice exam online is a full 180-question practice paper built to the real exam's domain weights, with every answer explained, with no sign-up and no credit card, and shows your score by topic at the end. The full 360-question bank, with every answer explained and cited to the exam sponsor's published content outline, is $14.99 for a 30-day pass that never renews.
How many questions are on the CertQuestUSA PMP Practice Exam (2026 Exam Content Outline) practice test?
360 questions total, split into 2 full papers of 180 each with no repeats across papers.
What topics does the PMP Practice Exam (2026 Exam Content Outline) test cover?
3 domains, with the heaviest weight on Process (41%), People (33%), and Business Environment (26%).
Where do CertQuestUSA's PMP Practice Exam (2026 Exam Content Outline) questions come from?
Primarily PMP ECO 2026 Process Task (41%) and PMP ECO 2026 People Task (33%) of this bank's citations -- computed directly from this exam's own question sources, not a generic description.
Is there a free PMP Practice Exam (2026 Exam Content Outline) practice test?
Yes -- one full 180-question practice paper built to the exam's domain weights, free with no sign-up, with every answer explained and a domain-by-domain score at the end.

Built to the three domains and 26 tasks of PMI's PMP Examination Content Outline, 2026 edition (the exam live from 9 July 2026), in the People 33 / Process 41 / Business Environment 26 weighting, with about 40 percent predictive and 60 percent agile or hybrid scenarios. Each paper is 180 questions. PMI does not publish a passing score; the readiness score shown here is our own estimate.

CertQuestUSA is an independent practice-test provider. PMI, PMP and PMBOK are marks of Project Management Institute, Inc., used here only to identify the exam. We are not affiliated with, sponsored by, or endorsed by PMI, and we are not a PMI Authorized Training Partner. Practice exams do not count toward the 35 contact hours of project management training PMI requires. All questions are original and written to the published outline; none are taken from the actual exam.